January 13, 2025
Environmental Update

Two Pivotal Montana Supreme Court Decisions Impact Industry

On Friday, January 3, 2025, the Montana Supreme Court issued a decision in MEIC v. DEQ (Laurel Generating Station), its second major decision on the Montana Environmental Policy Act (MEPA) in the last few weeks that affects permitting of energy projects in Montana. The Laurel Generating Station case provides Montana businesses with more insight into the practical application of the Court’s first decision in Held v. State, issued on December 18, 2024.

The Held Decision

This case was brought by youth Plaintiffs against the State and several agencies. The Plaintiffs sought wide-ranging relief, much of which the Court rejected. The Court found that:

  1. Montana Constitution’s “right to clean and helpful environment and environmental life support system includes a stable climate system…”;
  2. Plaintiffs had standing to bring the lawsuit even though there was not a particular project or permit at issue in the case; and
  3. Montana statutes prohibiting the State from considering greenhouse gas emissions (GHGs) in a MEPA analysis violate the Montana Constitution.

These three holdings mean that:

  1. A project that significantly impacts climate will require a full Environmental Impact Statement (EIS), rather than a smaller Environmental Assessment (EA). EIS’s require considerable investment of time and money, which impact a project’s timeline and budget.
  2. It will be easier for Plaintiffs to bring cases against industry projects, particularly those involving fossil fuels; and
  3. State agencies must now include a GHG analysis in EAs and EISs. While here the Court did not provide guidance about the level of detail required in an analysis, additional direction is revealed in its Lauren Generating Station decision, but we do not know how detailed that analysis must be.

The Laurel Generating Station Decision

This case questioned the sufficiency of an EA that DEQ performed on an air quality permit for a 175-megawatt natural gas power plant. Unlike Held, this was a specific project, with a specific EA, and the first practical application of Held. The Court found that DEQ was required to conduct a GHG analysis for this project but put some important sideboards on Held.

First, the Court stated, “We did not hold in Held, and do not hold here, that DEQ is required to analyze GHG emissions for every potential state action.” This is a very important distinction, as it means that smaller projects (like gravel pits) probably will not be constitutionally required to analyze GHGs in their EAs.

Second, the Court noted some specific facts that it relied on to determine a GHG was required in this case, which we can use to help predict when a GHG analysis will be required in future cases. The Court highlighted that this case “undisputedly involves a significant amount of CO2e emissions… from a fossil fuel [source] and generated hundreds of public concerns regarding potential impacts from those emissions.” These six facts directly connected this project to climate change. Although the Court will not demand these exact facts in all cases where a GHG analysis is required, it provides some level of reassurance to industry that there will need to be a connection between the project and GHG emissions.      

The Court also held that, because the case was brought under MEPA and not the Clean Air Act,[n]or do we hold that DEQ must regulate GHG emissions in an air quality permit application.” There was concern that this case could have shoehorned in, through MEPA, a requirement that DEQ adopt GHG emission standards, but it did not. The Court also reiterated that “MEPA does not confer regulatory authority beyond what is explicitly provided for in an existing statute.” This is an important reminder that MEPA is purely procedural. The Court also did not require that the permit be vacated while DEQ completes a new MEPA analysis.

Unfortunately for industry, the Court did hold that when a GHG analysis is required, “MEPA requires DEQ to analyze the direct, secondary, and cumulative impacts of this permitted action.” This means that going forward, when a GHG analysis is required, it will likely have a wide scope. However, there is modicum of comfort for industry. The Court found that DEQ’s error was not considering “impacts of the climate in Montana,” which may mean, for example, that considering the impacts of burning Montana coal in Korea is a step too far. The breadth and depth of the required analysis necessary for any project will certainly be the subject of future litigation.  

What Can Industry Do?

  • Engage with the Montana legislative session which began January 6, 2024. Twelve different bills have already been drafted for the legislature to review.
  • Consider conducting a tailored S.W.O.T. analysis of how these bills could affect your specific operations.
  • Help DEQ and other state agencies engage in the MEPA analysis of your projects. The first permits issued following these two cases undoubtedly will be targets for litigation. As permit applicants must provide agencies with the information necessary to conduct EAs or EISs, providing detailed data and GHG analysis to the agency up front may help with project approval.

Sarah M. Clerget was counsel for DEQ on both Held and Laurel Generating Station before joining Holland & Hart as Of Counsel and the Government Affairs Director for Montana.


This publication is designed to provide general information on pertinent legal topics. The statements made are provided for educational purposes only. They do not constitute legal or financial advice nor do they necessarily reflect the views of Holland & Hart LLP or any of its attorneys other than the author(s). This publication is not intended to create an attorney-client relationship between you and Holland & Hart LLP. Substantive changes in the law subsequent to the date of this publication might affect the analysis or commentary. Similarly, the analysis may differ depending on the jurisdiction or circumstances. If you have specific questions as to the application of the law to your activities, you should seek the advice of your legal counsel.

DISCLAIMER

Unless you are a current client of Holland & Hart LLP, please do not send any confidential information by email. If you are not a current client and send an email to an individual at Holland & Hart LLP, you acknowledge that we have no obligation to maintain the confidentiality of any information you submit to us, unless we have already agreed to represent you or we later agree to do so. Thus, we may represent a party adverse to you, even if the information you submit to us could be used against you in a matter, and even if you submitted it in a good faith effort to retain us.